Crimson sunsets, broken promises
By Siti Nurbaiyah Nadzmi
http://www.nst.com.my/streets/northern/crimson-sunsets-broken-promises-1.433790
THE 16-year-old residential area in Bandar Sungai Buaya does not have monsoon drains. We never have to worry of an untoward incident happening due to an open drainage system, because Bandar Sungai Buaya is designed to be "modern" with every precinct having a distinct house design conforming to its natural landscape.
How do you get to Bandar Sungai Buaya?
From Kuala Lumpur, take the North-South highway northbound, exit at Bukit Beruntung, then head towards Perodua and Tan Chong Motor automative plant before making a right turn at Kampung Koskan and then drive straight on to Bandar Sungai Buaya. At this particular stretch, drive slow to avoid hitting roaming cattle, long-tailed macaques or wild boars.
For a scenic route drive through Selayang towards Ipoh, by passing Templer Park, Hutan Lipur Kanching, Rawang town centre, to Kampung Sungai Choh (where former Miss Malaysia and celebrated actress Erra Fazira was born and raised), make a left turn the the T-junction, bypassing two automative plants before making a right turn at Kampung Koskan, then straight on to Bandar Sungai Buaya.
Either way, it will notch up 50 kilometres on your odometer, giving you about an hour's drive during off-peak hours, though it must be said that traffic congestion in Rawang can be legendary over the weekends.
When it was launched in 1996, developer Bandar Sungai Buaya Sdn Bhd sold the idea of a low-density living of eight units per acre, underground telecommunication cable system, a man-made lake, a club house and a recreational centre; and the sale brochure was emblazoned with "proposed" highway interchange which would make Kuala Lumpur a mere 18 minutes away.
It caught the imagination of many to own a property here and lead a suburban lifestyle, and I was one of them. Within days of launch, the first phase of the township was sold out.
The promise of this "modern suburban living" did not just extend to house buyers, but also to 363 Felda Sungai Buaya settlers who were here first to open the land with rubber plantation in 1964.
The entire township is built on a former Felda Sungai Buaya rubber estate, while the original settlement, Kampung Sungai Buaya is about three kilometres away from the newly-constructed township.
The Felda settlers were promised not just a suburban lifetyle but properties and a hefty sum in exchange of their land titles. The economic downturn in 1998 took all that away for all of us living in Bandar Sungai Buaya.
Due to the lack of funds, the developer halted the project, leaving Bandar Sungai Buaya a half-constructed township.
I found out soon enough from my neighbour who worked with Malaysian Highway Authority, that the proposal for the interchange was never really made. He never moved into the new house but sold it soon at the developer's price to cut his loss.
The developer's company was then liquidated in 2009, thus sealing the fate of Bandar Sungai Buaya as an abandoned township project.
Except for the Felda settlers, many of my neighbours decided to move out and live elsewhere. They could not stand the distance and the desolation of the township.
I, on the other hand, prefer waking up to the singing of tekukur (spotted dove), kingfisher, hummingbird, and murai on the trees, the stillness of the evening, the glorious crimson sunset over the hills and the light mist after the rain in Bandar Sungai Buaya.
Over the years, the 10,000 population neighbourhood grew on me. In the afternoon, the few stalls at the township junction "fragrants the air" with the smell of smoky grilled satay, bamboo tray steamed kueh pau, char kueh teow a la Sungai Buaya, banana leaf-wrapped nasi lemak and at the far end, petrol by the litre for motorcycles. You see, the nearest petrol station is 10 kilometres away. The nearest hospital is in Kuala Kubu Baru.
Like other housing areas, Bandar Sungai Buaya is no exception to a host of maintenance issues with the local council, in this case the Hulu Selangor District Council. The council, which covered the entire area of Hulu Selangor, was once awarded the broom for its inefficiency by a former Selangor Mentri Besar, a hugely unpopular gesture that was said to have cost Dr Mohamed Khir Toyo his political career.
While housebuyers like me suffer tremendous property value depreciation, the hardest blow fell on the Felda settlers. They did not just lose their land titles, for which they had worked for more than 30 years; now they also have no land to earn their livelihood.
It was a sad story debated over and over again at every election campaign; to be exact, four general elections and one by-election, switching representatives between Pakatan Rakyat and Barisan Nasional.
During the 2010 by-election campaigns, politicians promised that the highway interchange would be built, saying that the interchange would cut the journey by 20 kilometres and travelling time down to 20 minutes from Sungai Buaya toll gate to Jalan Duta exit.
You could forgive us for being sceptical because it has been 14 years since we first read the word "proposed" interchange on the house sales brochure that prompted us to buy a house here.
Several months after the by-election, a signboard popped up by the roadside announcing the construction of an interchange by PLUS with a scheduled delivery date on June 2013. It is now December.
The Sungai Buaya toll gate is barely two kilometres away from my house. It will make a significant change to my monthly expenses and time spent commuting to work and will definitely impact the lives of 100,000 people in Bandar Sungai Buaya, Kampung Sungai Buaya, Kampung Koskan, Kampung Sungai Choh and Serendah area.
The interchange may not immediately solve the Felda settlers land title issue, but surely this is a ray of hope to changes in Bandar Sungai Buaya and the surrounding areas.
Driving to work in Bangsar, I pass the construction site and see the construction progress daily. I pray that the completion of this interchange will finally connect Bandar Sungai Buaya, by distance and developments, to the rest of the world.
Pix by Mior Azfar Mior Kamarulbaid
Monday, October 29, 2012
Thursday, October 11, 2012
BASIKALTON AMAL 2012 - PIBG SK BANDAR SUNGAI BUAYA, RAWANG, SELANGOR
Dipersilakan menyertai BASIKALTON AMAL 2012 DI SK. BANDAR SUNGAI BUAYA, RAWANG, SELANGOR pada 10/11/12.
Sila layari untuk maklumat lanjut.........
http://basikalton.blogspot.com/
ALL ARE INVITED TO TAKE PART IN BASIKALTHON CHARITY PROGRAMME AT SK BANDAR SUNGAI BUAYA, RAWANG, SELANGOR ON 10/11/12.
PLEASE KLIK FOR MORE INFO....
http://basikalton.blogspot.com/
Monday, September 24, 2012
Mengumpul Dana Melalui Program Basikalthon Amal SK Bandar Sungai Buaya, 48010 Rawang, Selangor
Mohon Bantuan Untuk Menjayakanya!
Sila hubungi untuk maklumat lanjut:
1. Mohd Izuddin Mohd Ilias - 012 - 209 1127
2. Mustapha Kamal Kamaruddin - 019 - 341 7003
3. Mohamad Adli Hj Ibrahim - 019 - 221 0300
4. Sahiran Safiee - 012 - 589 8818
Saturday, September 8, 2012
June opening for Sg Buaya interchange, NST, 8 Sept 2012
RAWANG: Motorists from northern Selangor can expect to cut their travelling time to the Klang Valley by an hour when the Sungai Buaya Interchange is completed by June.
Works Minister Datuk Seri Shaziman Abu Mansor said work on the 1.5km-long interchange, which began last year, was half-complete.
"At 52 per cent completion, we are running ahead of schedule."
"Normally, projects of this scale will take 21/2 years to complete, but with the commitment of the developers and PLUS Expressways Berhad, we have managed to speed up development to just two years," he said during a briefing on the progress of the project at the interchange's construction site, here, yesterday.
The completion of the interchange will benefit some 120,000 residents at Sungai Buaya, Sungai Choh, Rawang Utara and Serendah, which will provide a direct access route from Sungai Buaya to the North-South Expressway.
Read more: June opening for Sg Buaya interchange - General - New Straits Times http://www.nst.com.my/nation/general/june-opening-for-sg-buaya-interchange-1.139873#ixzz25pziK2Ka
Persimpangan bertingkat Sungai Buaya dijangka siap Jun 2013, Harian Metro, 8 Sept 2012
BUKIT BERUNTUNG: Lebih 120,000 pengguna kenderaan di sekitar Sungai Buaya, Sungai Choh, Serendah dan Rawang Utara di sini, mendapat manfaat daripada Projek Pembinaan Persimpangan Bertingkat Baru Sungai Buaya yang dijangka siap sepenuhnya Jun tahun depan.
Menterinya, Datuk Seri Shaziman Abu Mansor berkata, projek pembinaan jambatan yang dimulakan pada 14 Jun tahun lalu dengan kos RM107 juta itu dapat memendekkan jarak perjalanan penduduk setempat ke ibu kota berbanding menggunakan laluan sedia ada.
“Ketika ini, penduduk di sekitar Sungai Buaya dan Sungai Choh terpaksa menggunakan Persimpangan Bertingkat Bukit Beruntung atau Persimpangan Bertingkat Rawang untuk memasuki Lebuhraya Utara-Selatan. Pembinaan persimpangan baru ini memberi manfaat dengan jarak dan masa perjalanan dipendekkan.
“Ini termasuk penjimatan petrol bagi perjalanan dua hala, selain penjimatan masa bagi perjalanan dua hala iaitu kira-kira 40 minit. Ketika ini perjalanan ke Kuala Lumpur mengambil masa kira-kira satu setengah jam,” katanya di sini, semalam.
Terdahulu Shaziman mengadakan lawatan kerja ke Tapak Projek Persimpangan Bertingkat dan Plaza Tol Sungai Buaya membabitkan empat zon iaitu zon A, B dan C, dengan menaiki kenderaan pacuan empat roda sejauh satu kilometer.
Menerusi lawatan berpandu itu, Shaziman diberikan penerangan ringkas mengenai status projek persimpangan bertingkat yang sedang dilaksanakan Plus Expressways Berhad (Plus) dengan bantuan kontraktor dengan peratusan pembinaan menjangkau 52 peratus siap.
Dengan keupayaan kontraktor menjalankan kerja pembinaan melebihi empat peratus lebih awal dan mendahului jadual ditetapkan sebanyak 40 peratus menyebabkan kementerian terbabit optimis menyiapkannya pada Jun tahun depan.
Artikel ini disiarkan pada : 2012/09/08
Thursday, November 17, 2011
Keputusan UPSR Sek Keb Bandar Sungai Buaya
Sukacita dimaklumkan bahawa keputusan UPSR SK BSB adalah seperti berikut:
25 Pelajar 5A
20 Pelajar 4A 1B
GPS 2.08
Peratus Lulus ialah 77.6%
Tahniah kepada Semua.
25 Pelajar 5A
20 Pelajar 4A 1B
GPS 2.08
Peratus Lulus ialah 77.6%
Tahniah kepada Semua.
Sunday, July 24, 2011
Wednesday, July 6, 2011
Monday, June 20, 2011
Sunday, June 19, 2011
Berita dari MSTAR, 19 Jun 2011
mStar Online > BERITA Sunday June 19, 2011
Persimpangan Bertingkat Sungai Buaya Jimat Masa 40 Minit Untuk Ke Lembah Klang
RAWANG: Lebih 100,000 pengguna di sekitar kawasan Sungai Buaya, Sungai Choh, Serendah dan utara Rawang akan dapat menjimatkan masa antara 40 minit hingga satu jam untuk ke Lembah Klang apabila Persimpangan Bertingkat Sungai Buaya dekat sini siap pada Jun 2013.
Menteri Kerja Raya Datuk Shaziman Abu Mansor berkata, apabila persimpangan sepanjang 1.5 kilometer dengan kos RM87 juta itu siap, PLUS Expressways Berhad (PLUS) akan menyelia kutipan tol di persimpangan berkenaan.
Menteri Kerja Raya Datuk Shaziman Abu Mansor berkata, apabila persimpangan sepanjang 1.5 kilometer dengan kos RM87 juta itu siap, PLUS Expressways Berhad (PLUS) akan menyelia kutipan tol di persimpangan berkenaan.
"Kalau diikutkan harga sebenar pembinaan persimpangan tersebut ialah lebih dari RM100 juta tetapi kerajaan pusat prihatin dengan membayar tambahan sebanyak RM20 juta untuk pengambilihan tanah ini manakala kos pembinaan(persimpangan) ditanggung oleh pihak Plus," katanya pada majlis pecah tanah persimpangan berkenaan di Bandar Baru Sungai Buaya, di sini, Ahad.
Sebelum ini, penduduk di sekitar Sungai Buaya dan Sungai Choh terpaksa menggunakan Persimpangan Bertingkat Bukit Beruntung atau Persimpangan Bertingkat Rawang untuk memasuki Lebuhraya Utara-Selatan.
Projek persimpangan berkenaan yang mula dibina pada 14 Jun tahun lepas terletak di KM434.7 di Lebuhraya Utara-Selatan iaitu di antara Persimpangan Bertingkat Rawang di KM444 dan Persimpangan Bertingkat Bukit Beruntung di KM428.
Shaziman berkata kos sebanyak RM87 juta itu bukan sahaja melibatkan pembinaan persimpangan berkenaan malahan turut meliputi pembinaan lorong tol, bangunan pusat khidmat pelanggan, surau, tandas awam serta tempat meletak kenderaan.
Shaziman berkata persimpangan berkenan turut memberi kemudahan akses bagi dua aktiviti industri utama iaitu kilang Perodua dan Tan Chong Motor serta kira-kira 100 industri kecil dan sederhana yang sedia ada berhampiran kawasan Sungai Buaya dan kawasan persekitaran.
Bercakap kepada pemberita kemudiannya, Shaziman berkata kerajaan masih memikirkan kadar tol yang terbaik bagi persimpangan itu berdasarkan kadar tol semasa di beberapa plaza tol di negara ini bagi memastikan pengguna yang melalui persimpangan berkenaan akan dikenakan caj pada kadar yang berpatutan.
Sementara itu, Yang Dipertua Persatuan Penduduk Bandar Baru Sungai Buaya Datuk Rosli Hashim berharap persimpangan bertingkat itu akan merancakkan lagi pertumbuhan ekonomi dengan kemasukan pelabur di kawasan berkenaan dan seterusnya mewujudkan lebih banyak peluang pekerjaan kepada penduduk sekitar.- BERNAMA